    Patch Deployment

    Hemal Rookie

      Hi Team

       

      During Patch Tuesday week, we patch our IT machines before our scheduled deployment on the weekend. We patch our machines, and they reboot as per normal, is there way to stop the second reboot on the weekend when the scheduled patches run, as the machine have been patched.

       

      Thanks

       

      Hemal

        • 1. Re: Patch Deployment
          cwinning CommunityTeam

          Hello,

           

          Is there a scheduled scan with automatic deployment scheduled? You can cancel this from Manage > Scheduled Console Tasks.

          Is there a scheduled deployment against these machines? You can cancel a scheduled deployment if it hasn't started processing. Cancel Deployments

           

          Thanks,

          Charles

          • 2. Re: Patch Deployment
            Hemal Rookie

            Hi Charles

             

            Thanks for coming back to me. We have secluded deployment in place, but for our IT Machines we patch them before, to test the updates and make sure all okay. So we manually update them outside the secluded plans, but then on the weekend the machines re-scan and get rebooted again. So wanted to know if can avoid that for the patched machines.

             

            Thanks 

            • 3. Re: Patch Deployment
              cwinning CommunityTeam

              Hello,

               

              The patched machines will scan, deploy and reboot if you have it scheduled to do so. They will only deploy and reboot if a missing patch is detected and installed on them. Did you use a Machine Group to schedule this?  If yes, you could attempt Exclude the machine in the Machine Group. How To Exclude Machines During A Scan

               